Excavation Permit
Temporary permission to undertake regulated excavation works. KCCA specifically provides for excavation permits, including excavations exceeding 3 metres.
Where to apply is being confirmed.Kampala Capital City Authority (KCCA) directs applicants to KCCA Excavation Permit Form; we are confirming the exact channel and will publish it here. Contact Kampala Capital City Authority (KCCA)
Who needs it
Developers/contractors undertaking regulated excavation works.
Excavation permit is temporary and may be revoked for non-compliance.
Instrument type: Construction / Excavation Permit
Related requirements noted by the issuing authority: Planning and building approval
Fees
Fee not clearly stated on the current KCCA published physical-planning fee schedule; verify with KCCA before entering a fee figure.
Do not substitute an estimated fee.
Documents required
- Application form; property information; proposed excavation description; excavation methodology/safety plan where applicable; approved planning/building documents.
Steps to apply
- 1Planning/building approval
- 2Submit excavation application
- 3Technical assessment
- 4Approval
- 5Permit
Key facts
- Processing time
- Subject to technical assessment.
- Validity / renewal
- Temporary; linked to approved excavation works.
- Legal basis
- Physical Planning Act, 2010; Building Control Act/Regulations; applicable public health and safety laws.