Who needs it

Property owners/developers undertaking construction, alteration, addition or other development.

Development must comply with zoning, planning and building requirements.

Instrument type: Development / Construction Permit

Related requirements noted by the issuing authority: Occupation permit, renovation permit, demolition permit, hoarding permit, excavation permit, chain-link permit, etc.

Fees

Architectural plans inspection: UGX 1,000 per m² of ground-floor area; structural plans inspection: UGX 30,000 per suspended slab; other applicable fees depend on the development.

Fees are generally subject to VAT unless otherwise specified.

Documents required

  • Land ownership documents, architectural/structural plans, application documents and other documents required by KCCA.

Steps to apply

  1. 1Engage relevant professionals
  2. 2Prepare plans
  3. 3Submit application
  4. 4Technical/planning review
  5. 5Approval
  6. 6Payment of applicable fees.
Apply on the KCCA Smart Permit system

Key facts

Processing time
Depends on nature and complexity of application.
Validity / renewal
Building plan approval lapses where development has not commenced within 18 months, or where commenced but not completed within the prescribed period; resumption approval may be required.
Legal basis
Physical Planning Act, 2010; Building Control Act, 2013; Building Control Regulations, 2020 and related planning instruments.
Owner: KCCA Directorate of Physical PlanningLast reviewed: 18 August 2026